Project Status Reports

27/06/2024

Creating effective project status reports involves providing a clear, concise, and comprehensive overview of the project's progress, current status, and any issues that need attention.  

Time Driven Reports

Weekly/Fortnightly/Monthly status Report Format

 Here's a guide to creating an effective project status report (Weekly, Fortnightly or Monthly)

Structure of a Project Status Report

Project Title: Website Redesign
Date: June 27, 2024 

Executive Summary

  • Brief overview of the project's purpose and objectives
  • High-level summary of the current status

Current Status ( Details of Task Accomplished in this reporting Period)

  • Progress Summary: What has been completed since the last report?
  • Schedule Status: Is the project on schedule, ahead, or behind? Include a timeline if necessary.
  • Budget Status: Is the project on budget, over, or under? Provide details on expenditures.
  • Forecast : Based on the current status
  • Achievements List significant accomplishments since the last report., Mention any milestones reached.

Upcoming Tasks (Task planned for the next reporting period)

  • Outline key tasks and milestones expected in the next reporting period.
  • Assign responsibilities if applicable.

Issues and Risks

  • Detail any problems currently affecting the project and the resolution plan
  • Identify potential risks and their response  plans.

Lesson Learned 

  • Any learning during the reporting period


Sample Weekly Project Status Report

Project Title: Website Redesign
Date: June 27, 2024

Executive Summary

The website redesign project aims to update the company's online presence to improve user experience and increase engagement. This week, significant progress was made in the design phase with initial wireframes being completed and approved.

Current Status ( Details of Task Accomplished in this reporting Period)

  • Progress Summary: The design phase is 50% complete. Wireframes for the homepage and main sections have been approved.
  • Schedule Status: On schedule
  • Budget Status: On budget
  • Forecast : Based on the current progress , its seems that the project will complete on time 

Achievements

  • Completed and approved wireframes for the homepage and main sections.
  • Conducted user feedback sessions on initial designs.

Upcoming Tasks

  • Finalize detailed design mockups for the homepage and main sections.
  • Begin initial development work on the approved designs.
  • Prepare for the next stakeholder review meeting.

Issues and Risks

  • Current Issues: Minor delays in receiving feedback from stakeholders. No significant impact on the overall schedule.
  • Risk Management: Potential delay in finalizing design mockups due to stakeholder availability. Mitigation: Schedule additional review meetings and set clear deadlines for feedback.

Lesson Learned

  • The newly used tool was useful , can be used in future
  • Bad experience with a Vendor, not recommend for more work

Event Driven Reports

Project Closure Report

A project closure report marks the official completion of a project and ensures that all aspects are wrapped up properly. It includes a summary of the project's achievements, final deliverables, lessons learned, and recommendations for future projects.

Structure of a Project Closure Report

1. Executive Summary

Provide a brief overview of the project, its objectives, and the final outcomes.

  • Objective: [Summarize the initial goal of the project]
  • Outcome: [Highlight key achievements or final deliverables]
  • Duration: [Start Date - End Date]
  • Budget: [Initial vs. actual budget]

2. Project Performance

Evaluate how the project performed against its goals.

2.1 Objectives Achievement

Objective---------- -------------Status--------------- ----Remarks
[Objective 1]                          Achieved/Partial         [Provide comments]
[Objective 2]                         Not Achieved               [Provide reasons and lessons learned]

2.2 Budget Performance

Category------------ Budgeted------------ Actual----------- Variance
[Category 1]                [Amount]                     [Amount]                [Over/Under]

2.3 Timeline Performance

Milestone--------- Planned Date----------- Actual Date------------ Remarks
[Milestone 1]               [Date]                                 [Date]                             [Remarks]

3. Key Deliverables

List the final deliverables and their statuses.

Deliverable----------------- Status ----------------------Owner/Stakeholder
[Deliverable 1]                     Completed                                     [Name/Team]
[Deliverable 2]                    Not Completed                              [Name/Team]

4. Lessons Learned

Summarize insights gained during the project.

4.1 What Worked Well:

  • [Highlight successful practices or tools]

4.2 Challenges:

  • [List major obstacles or issues encountered]

4.3 Recommendations:

  • [Propose actions for future projects based on this experience]

5. Outstanding Items

List any open issues or tasks that need to be addressed post-project.

Item ----  -----------------   Owner  ------------------Deadline

[Task/Issue]                       [Name/Team]                           [Date]  

6. Stakeholder Feedback

  • CEO: "The new website is a game-changer for our digital presence. Excellent work!"
  • Marketing Director: "The design is visually stunning and easy to navigate. Kudos to the team!"

7. Final Approval

Name------------ ------------Role-------------------------------- Signature Date
Sarah Thompson                Project Manager                                     [Signature] Dec 8, 2024
John Harris                           Marketing Director                                 [Signature] Dec 8, 2024

8. Archiving and Handover

  • Documents archived at: SharePoint > Projects > Website Redesign
  • Handover details: Maintenance responsibilities transferred to IT Support Team.


Project Closure Report

Project Name: Website Redesign Initiative
Project Manager: Sarah Thompson
Date: December 8, 2024

1. Executive Summary

The Website Redesign Initiative aimed to modernize the company's online presence to enhance user experience and drive customer engagement. The project delivered a fully redesigned, mobile-responsive website with improved navigation, faster load times, and a new visual design.

  • Objective: To launch a user-friendly and visually appealing website by December 1, 2024.
  • Outcome: The website was successfully launched on November 25, 2024, five days ahead of schedule.
  • Duration: April 1, 2024 – November 25, 2024
  • Budget: $150,000 (budgeted) vs. $145,000 (actual).

2. Project Performance

2.1 Objectives Achievement

Objective.----------------------------- ----Status---------------------------------------- Remarks
Create a modern visual design                    Achieved                                                             Delivered a fresh and branded look.
Improve mobile responsiveness                 Achieved                                                             Pages load within 2 seconds on mobile.
Enhance navigation structure                      Achieved                                                              Added a mega menu for ease of use.

2.2 Budget Performance

Category-------------------------- Budgeted ------------------------Actual--------------- Variance
Design & Development                   $100,000                                          $98,000                         $2,000
Content Creation                              $30,000                                            $32,000                         -$2,000
Testing                                                $20,000                                            $15,000                          $5,000

2.3 Timeline Performance

Milestone------------------ Planned Date------------------------- Actual Date------------- Remarks
Kickoff                                     Meeting April 1, 2024                              April 1, 2024                          On time
Wireframe Approval             May 15, 2024                                            May 20, 2024                        Minor delay
Beta Testing                           October 1, 2024                                       September 28, 2024            Ahead of schedule
Website Launch                    December 1, 2024                                   November 25, 2024             Early delivery

3. Key Deliverables

Deliverable--------------------------- Status-------------------------- Owner/Stakeholder
Redesigned website                          Completed                                          Marketing Team
User testing report                             Completed                                          QA Team
SEO optimization plan                       Completed                                          SEO Specialist

4. Lessons Learned

4.1 What Worked Well:

  • Cross-functional collaboration was seamless due to regular stand-ups and effective use of project management tools.
  • Early user testing provided critical insights that improved the design before launch.

4.2 Challenges:

  • Content creation took longer than expected due to delays in stakeholder approvals.
  • The wireframing process required additional iterations to align with the brand's vision.

4.3 Recommendations:

  • Establish a streamlined content approval process to avoid delays.
  • Incorporate more frequent checkpoints during the design phase for alignment.

5. Outstanding Items

Item---------------------------------- ------- Owner----------------------------------------- Deadline
Monitor website performance                         IT Team                                                                    Ongoing
Conduct post-launch feedback survey         Marketing Team                                                     January 15, 2025

6. Stakeholder Feedback

  • CEO: "The new website is a game-changer for our digital presence. Excellent work!"
  • Marketing Director: "The design is visually stunning and easy to navigate. Kudos to the team!"

7. Final Approval

Name Role-------------------------- Signature------------------------------ Date
Sarah Thompson                                 Project Manager                                  [Signature] Dec 8, 2024
John Harris                                           Marketing Director                               [Signature] Dec 8, 2024

8. Archiving and Handover

  • Documents archived at: SharePoint > Projects > Website Redesign
  • Handover details: Maintenance responsibilities transferred to IT Support Team.

End Stage /End Phase Report

End Stage Report

Project Name: Mobile App Development for E-Commerce
Stage Name: Development Stage
Date: December 8, 2024
Project Manager: Alex Morgan

1. Summary of Stage Performance

1.1 Objectives Achieved

  • Developed core functionalities for the mobile app, including user registration, product catalog, and checkout process.
  • Integrated payment gateway with successful testing.
  • Conducted initial user testing with feedback incorporated into the next stage.

1.2 Key Deliverables

Deliverable----------------------- ----Status------------------------------------------- Remarks
User Registration Module                  Completed                                               Met requirements; minor UI fixes needed.
Product Catalog Display                    Completed                                               Successfully displays product data.
Payment Gateway Integration          Completed                                                Fully functional and tested.

1.3 Stage Milestones

Milestone --------------------------------Planned Date---------------------- Actual Date --------------------Variance
Start of Development Stage                   October 1, 2024                                     October 1, 2024                             On time
Completion of Development Stage      December 1, 2024                                 December 5, 2024                        - 4 days

2. Issues and Risks

2.1 Issues Faced

Issue ----- --------------------------------------Impact--------------------------------Resolution
Delayed APIs from third-party vendor               Medium                                          Extended timeline by 4 days to integrate.
Unexpected bugs in payment module              High                                                Additional testing conducted, resolved.

2.2 Risks Identified for Next Stage

Risk--------------------------------------Likelihood---------------------- Impact-----------------------Mitigation Plan
Resource unavailability                            Medium                                          High                                       Allocate backup resources early.
Scalability of the product catalog          Low                                                  Medium                                Perform load testing in the next stage.

3. Forecast for Next Stage

3.1 Timeline Forecast

The next stage (Testing & Deployment) is planned to start on December 10, 2024, and end on January 15, 2025. Considering current progress, the timeline is expected to remain unchanged.

3.2 Budget Forecast

Stage------------------------------- Planned Budget--------------------Actual Cost (to Date)-------------- Forecasted Cost
Development                                      $100,000                                                $98,000                                               $100,000
Testing & Deployment                      $50,000                                                  0 $                                                         $50,000

3.3 Deliverable Forecast

The key deliverables for the next stage include:

  1. Completion of system-wide testing.
  2. Deployment of the app on both iOS and Android platforms.
  3. Initial user onboarding for beta testing.

4. Lessons Learned

  • Early collaboration with third-party vendors is essential to avoid integration delays.
  • A dedicated QA resource during development improves efficiency by identifying bugs earlier.

5. Approval and Recommendations

The Development Stage has been completed successfully, albeit with minor delays. The project is on track for the Testing & Deployment stage with the following recommendations:

  1. Conduct detailed testing of the product catalog to ensure scalability.
  2. Increase contingency planning for vendor dependencies in the next stage.

Name................................................ Role............................................... Signature......................................... Date
Alex Morgan                      Project Manager                         [Signature]                                  Dec 8, 2024
Samantha Lee                  Product Owner                            [Signature]                                  Dec 8, 2024

6. Documentation and Handover

  • All stage documents are archived on SharePoint: Project > Development Stage.
  • Handover notes shared with the QA team for the Testing & Deployment stage.

Escalation Report Template

An escalation report is used to formally raise an issue or risk to a higher authority when it cannot be resolved at the current level. Below is a template for creating an effective escalation report.

Escalation Report
Project Name: [Insert Project Name]
Report Date: [Insert Date]
Reported By: [Your Name]
Escalated To: [Name/Role of Recipient]

1. Summary of the Issue

Provide a concise overview of the issue being escalated:

  • Issue Description: [Briefly describe the issue or risk.]
  • Impact: [Explain the impact on the project, such as delays, cost overruns, or stakeholder dissatisfaction.]
  • Urgency: [Classify as High/Medium/Low with justification.]

2. Background Information

  • When Identified: [Date the issue was first noticed.]
  • Current Status: [What actions have been taken so far?]
  • Attempts to Resolve: [List solutions attempted and why they didn't work.]

3. Details of the Escalation

3.1 Root Cause Analysis

Explain the underlying cause(s) of the issue:

  • [Describe any factors contributing to the problem.]

3.2 Key Stakeholders Affected

  • [List departments, teams, or individuals impacted by the issue.]

3.3 Dependencies

  • [Mention if the issue depends on external vendors, other teams, or tools.]

4. Impact Assessment

4.1 Current Impact:

  • Scope: [Which project areas or deliverables are impacted?]
  • Timeline: [How does this affect the project schedule?]
  • Budget: [Is there any cost overrun linked to this issue?]

4.2 Future Risks:

  • [Highlight risks if the issue is not resolved promptly.]

5. Recommended Actions

Propose potential solutions or actions needed to address the escalation:

Action ---------------------------Owner ---------------------------Timeline ---------------------------Remarks
[Proposed Action 1]                     [Responsible Party]                        [Target Date]                                       [Comments]
[Proposed Action 2]                    [Responsible Party]                         [Target Date]                                        [Comments]

6. Supporting Evidence

Include any relevant documents, screenshots, logs, or data to support the escalation:

  • [Attachment/File Name 1]
  • [Attachment/File Name 2]

Top 5 Risks Report

Project Name: E-Commerce Website Revamp
Report Date: December 8, 2024
Project Manager: James Carter

1. Risk: Payment Gateway Integration Failure

  • Description:
    The integration of the payment gateway with the website is critical for enabling transactions. A failure to integrate successfully could prevent the website from processing payments, delaying the project launch.
  • Impact:
    High. If unresolved, this could delay the entire project, including marketing and client go-live.
  • Likelihood: High (due to API issues and communication delays with the third-party provider).
  • Mitigation Plan:
    • Escalate the issue with the third-party payment provider.
    • Investigate backup payment solutions or providers.
    • Perform thorough testing once resolved.
  • Owner: James Carter, Project Manager

2. Risk: Resource Shortages in Development Team

  • Description:
    Key developers and designers may not be available due to other concurrent projects or personal leave, which could cause delays in project milestones.
  • Impact:
    Medium to High. Delays in key deliverables, potentially affecting the timeline.
  • Likelihood: Medium (due to ongoing resource allocation challenges).
  • Mitigation Plan:
    • Cross-train team members to increase flexibility.
    • Engage with external contractors if necessary.
    • Adjust project timeline or reallocate internal resources.
  • Owner: Sarah Lee, Senior Developer

3. Risk: Scope Creep

  • Description:
    Uncontrolled changes to the project scope, such as additional features or requests from the client, could impact the timeline, budget, and overall quality of the product.
  • Impact:
    High. Could lead to project delays, budget overruns, and unmet client expectations.
  • Likelihood: High (common in projects with frequent client requests).
  • Mitigation Plan:
    • Implement strict change control processes.
    • Regularly review the scope with the client and stakeholders.
    • Prioritize critical deliverables and adjust expectations as needed.
  • Owner: James Carter, Project Manager

4. Risk: Third-Party Vendor Delays

  • Description:
    Delays from third-party vendors (e.g., hosting services, APIs) could cause disruptions in project timelines and quality.
  • Impact:
    Medium to High. Could cause delays in development or even prevent the project from meeting its go-live target.
  • Likelihood: Medium (due to reliance on external vendors).
  • Mitigation Plan:
    • Establish clear contracts with SLAs (Service Level Agreements).
    • Regularly track progress with vendors and maintain open communication.
    • Identify backup vendors in case of continued delays.
  • Owner: Sarah Lee, Vendor Relations Manager

5. Risk: Data Security and Compliance Issues

  • Description:
    Failure to meet data security standards and compliance regulations (such as GDPR or PCI-DSS for payment processing) could result in legal issues, fines, and reputational damage.
  • Impact:
    High. Potential legal consequences, loss of trust, and significant financial penalties.
  • Likelihood: Medium to High (due to changing compliance requirements).
  • Mitigation Plan:
    • Conduct a thorough security audit before go-live.
    • Ensure compliance with relevant standards and regulations.
    • Regularly update security protocols and training for the team.
  • Owner: Jessica Roberts, Compliance Officer

Risk Summary Table

Risk----------------------------- ---------Likelihood ----------Impact------------- Mitigation Plan ---------------------           Owner
Payment Gateway Integration                   Failure High            High         Escalate to payment provider, explore alternatives    James Carter
Resource Shortages in Development      Medium                  Medium   Cross-train, engage contractors, adjust timeline         Sarah Lee
Scope Creep                                                 High                         High         Change control, prioritize critical deliverables            James Carter
Third-Party Vendor Delays                          Medium                  Medium   Establish SLAs, track vendor progress                         Sarah Lee
Data Security and Compliance Issues      Medium                  High          Security audit, ensure regulatory compliance           Jessica R

Next Steps:

  • Regularly monitor these risks during project meetings.
  • Implement mitigation strategies and update the risk register as necessary.